Project Description
| MEP Contractor | Faisal Electro-Mechanical Co. Ltd. |
| Location | Dammam, KSA |
| End User | Ministry of Higher Education |
| Client | Dammam University |
| Project Management | University PM |
| Consultant | |
| Type of Project | District Cooling & Infrastructure |
| Total Value (SAR) | 215 Million Saudi Riyal |
| Start Date | Aug, 2014 |
| Finish Date | Sep, 2016 |
| Total Land Area | |
| Total Built-up Area |
Work Description
Civil, Mechanical, & Electrical Infrastructure Works
Scope of Work
- Excavation & Backfilling: 115,000 m³ & 52,000 m³
- Total length: 952 m
- Width: 30 m
- Second Pile Shoring System
- Tensile Piles Under Raft
- Concrete and Road Works