Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant Saud Consult
Type of Project District Cooling & Infrastructure
Total Value (SAR) 101.39 Million Saudi Riyal
Start Date Mar, 2005
Finish Date Nov, 2007
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Excavation & Back-filling of 1,362,694 cu. mtr. of Soil,
  • Construction of 107,700 LM of Flexible Pavements
  • 92,200 LM of Curbs & Gutters and 61,000 sq. mtrs. of Sidewalks.
  • 769 LM of Underground Piping (FRP) were laid, and Water Tank of 1,800 cu.mtr. was constructed.
  • R.O Plant of 600 cu.mtr. / day capacity was installed with Water Well and 14.13 KM of Water Network Piping.
  • Sewage Treatment Plant (STP) and Sewage Lift Station is provided with
  • Installation of 5.12 KM of Sanitary Sewage Piping.
  • 5.34 KM of Irrigation Piping has been laid.
  • 50 mtrs. of LPG Pipes (above ground) have been installed with 2 nos. of LPG Tanks of 40,000 USG capacity.
  • 2 nos. of Centrifugal Chillers and 2 nos. of Cooling Towers have also been erected.
  • Electrical Works include: Installation of Power & Distribution Transformers,
  • LV Switchgear, and Street Lighting Poles
  • Communication & Data Processing Equipment, Telephone & Inter-com System.
  • Building Automation & Controls and Security Surveillance System were also added.