Project Description
Contractor | Faisal Electro-Mechanical Co. Ltd. |
Location | Jubail, KSA |
End User | Royal Commission for Jubail and Yanbu |
Client | Royal Commission for Jubail and Yanbu |
Project Management | |
Consultant | |
Type of Project | District Cooling & Infrastructure |
Total Value (SAR) | 159.73 Million Saudi Riyal |
Start Date | Jan, 2018 |
Finish Date | Aug, 2020 |
Total Land Area | |
Total Built-up Area |
Work Description
Civil, Electrical & Mechanical works
Scope of Work
Site Infrastructure Works
- Storm Water Piping System: 800 m.
- Potable and Fire Water Piping System: 700 m.
- Sanitary Water Piping System: 500 m.
- Break Water Storage Steel Tank: 1 no. 6 m dia. Capacity 150 m³.
- Potable Water Storage Steel Tank: 1 no. 9 m dia. Capacity 400 m³.
- Make-Up Water Storage Steel Tanks: 2 nos. 14 m dia. Capacity 2,275 m³.
- Thermal Energy Storage Steel Tank: 1 no. 23 m dia. Capacity 24,000 ton/hr.
Chiller Plant
- Electric Operated Overhead Cranes: 2 nos. Lifting Capacity 15 ton.
- Series Counter Flow Water Cooled Centrifugal Chillers: 6 nos. Capacity 3,000 TR each (TOTAL 18,000 TR).
- Induced Draft Field Erected Counter Flow Cooling Towers: 3 nos. Capacity 12,400 GPM.
- Chilled Water Pumps: 3 nos. TDH 3 bar, Capacity 9,000 GPM.
- Condenser Water Pumps: 3 nos. TDH 4 bar, Capacity 9,000 GPM.
- MV Switchgears: 2 nos. 4.16 kV and 3 nos. 13.8 kV
- Diesel Generator: 1 no. 300 kVA
Pump Stations
- Make-Up Water Pumps: 4 nos. TDH 2 bar, Capacity 376 GPM
- Fire Pumps: 2 nos. TDH 9 bar, Capacity 750 GPM
- Submersible Pumps: 2 nos. TDH 3.5 bar, Capacity 1,200 GPM
- Excavation and Backfilling
- Expansion Tanks
- Basket Strainers
- Firefighting FM200 Clean Agent System
- Air Handling Units, Package Units, Fan Coil Units and Exhaust Fans
- Chemical Treatment System
- Access Control System & SCADA
- Area Lightning System
- Telecommunication System