Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Riyadh, KSA
End User Ministry of Higher Education
Client King Saud University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 21.67 Million Saudi Riyal
Start Date Feb, 2012
Finish Date Nov, 2013
Total Land Area
Total Built-up Area

Work Description

Mechanical & Electrical Works

Scope of Work

  • Closed Loop Type Cooling Towers: 9 nos. heat rejection 7,497,000 BTU / Hr each water flow 1,500 GPM, 60HP fan motor.
  • Water-Cooled Centrifugal Chillers: 3 nos. Capacity 1,500 TR each (TOTAL 4,500 TR).
  • Chilled Water Pumps: 3 nos. centrifugal constant flow double suction split case type water flow rate 2,000 GPM @126ft.TDH, 200 HP motor, including control panel.
  • Condenser Pumps: 3 nos. centrifugal constant flow double suction split case type water flow rate 4,500 GPM @130ft.TDH, 300 HP motor, including control panel.
  • Supply and Install One Distribution Pump Centrifugal Constant Flow Double Suction Split Case Type Water Flow Rate: 4,400 GPM @100ft.TDH, 200 HP motor, including control panel.