Removal of Cement Mortar Lining Debris in Line (B) between PS1 & PS2 of Riyadh Water Transmission System

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Saline Water Conversation Corp. (SWCC)
Client Saline Water Conversation Corp. (SWCC)
Project Management
Consultant
Type of Project Industrial
Total Value (SAR) 6.9 Million Saudi Riyal
Start Date 20 Jan, 2021
Finish Date 28 Jan, 2021
Total Land Area
Total Built-up Area

Work Description

  • Removal of Cement Mortar Lining Debris in Line (B) between PS1 & PS2 of Riyadh Water Transmission System, within 9 days, 24-hour duty, consisting of Excavation & Wrapping Removal, Draining, Cutting, Cleaning, Fit-up and Welding & NDT.

P&C of Sea Water Cooling Supply Piping for Royal Commission at Ras Al-Khair

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Ras Al Khair, KSA
End User Royal Commission for Jubail and Yanbu
Client Royal Commission for Jubail and Yanbu
Project Management
Consultant Bechtel
Type of Project Pipeline
Total Value (SAR) 30.19 Million Saudi Riyal
Start Date May, 2020 (Notice to Proceed)
Finish Date May, 2021
Total Land Area
Total Built-up Area

Work Description

Infrastructure Pipeline

Scope of Work

  • Installation and Testing & Commissioning of 6,000 LM pf 1600 mm dia pipe

Currie & Brown التصميم الداخلي والتأثيث لشركة

تفاصيل المشروع

شركة فيصل للأعمال الكهربائية والميكانيكية المقاول
الرياض، المملكة العربية السعودية الموقع
Currie & Brown المستهلك
Currie & Brown العميل
 IDS Development Management and Consultancy إدارة المشروع
IDS Development Management and Consultancy المستشار
مبنى مكاتب نوع المشروع
750,000 SR القيمة الإجمالية
January, 2020 تاريخ البدء
October, 2020 تاريخ الانتهاء
إجمالي مساحة الأرض
650 m2 إجمالي المساحة المبنية

طبيعة العمل

.تصميم داخلي وأعمال كهربائية وميكانيكية

نطاق العمل

  • توريد وتركيب الفواصل الزجاجية.
  • توريد وتركيب أسقف وحوائط جبسية.
  • إعادة تأهيل وتحسين نظام التدفئة والتهوية وتكييف الهواء.
  • إعادة تأهيل وتحسين نظام مرشات وإنذار الحريق.
  • Rehabilitation and Improvement of IP Data System
  • إعادة تأهيل وتحسين نظام كاميرات المراقبة الأمنية.
  • إعادة تأهيل وتحسين نظام التحكم في الدخول والخروج.
  • إعادة تأهيل وتحسين نظام توزيع الطاقة الكهربائية.
  • توريد وتركيب أثاث المكتب.

Replacement D31-K-0523A Blower Project @ Shedgum Gas Plant, Saudi Aramco

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Shedgum, KSA
End User Saudi Aramco
Client Saudi Aramco
Project Management
Consultant
Type of Project Industrial
Total Value (SAR) 1.9 Million Saudi Riyal
Start Date Dec, 2019
Finish Date Oct, 2020
Total Land Area
Total Built-up Area

Work Description

  • To replace the existing D31-K-0523A Blower with all required expansion bellows & isolation requirements

تصميم، وبناء، وتأثيث هيئة تطوير بوابة الدرعية

تفاصيل المشروع

FEMCO & SASEL CONSORTIUM المقاول
المملكة العربية السعودبة، الرياض الموقع
هيئة تطوير بوابة الدرعية المستهلك
هيئة تطوير بوابة الدرعية العميل
Faithful+Gould إدارة المشروع
خطيب وعلمي المستشار
مبنى مكاتب نوع المشروع
89,000,000 SR القيمة الإجمالية
July, 2019 تاريخ البدء
June, 2020 تاريخ الانتهاء
45,000m2 إجمالي مساحة الأرض
12,000m2 إجمالي المساحة المبنية

طبيعة العمل

.أعمال كهربائية، وميكانيكية، وبنية تحتية

نطاق العمل

  • أعمال أسفلت بمساحة 45,000m2 ومواقف سيارات بمساحة 37,000m2.
  • شبكة مياه الشرب والري والصرف الصحي والعواصف ومكافحة الحرائق.
  • بناء طابقين بمساحة 12,000 من الهيكل الصلب.
  • بناء وتأثيث مبنى الحرَّاس الرئيسي.
  • توريد وتركيب أثاث المكتب.
  • جميع الأعمال المدنية، والمعمارية، والكهروميكانيكية المرتبطة بالمشروع.

Chilled Water Line – SWCC

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jubail, KSA
End User Saline Water Conversion Corporation (SWCC)
Client Saline Water Conversion Corporation (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 5.18 Million Saudi Riyal
Start Date May, 2019
Finish Date Feb, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical Work

Scope of Work

  • Supply and Installation New GRV Pipes & Fittings
  • Supply and Installation of Power Pack for DN 900 Butterfly valves
  • Fabrication of GRP Pipe supports.
  • Civil Works; Concrete Work for Pipes Foundation, Asphalt Cutting, Excavation  and Back filling work

Infrastructure of University City (Phase 3) Rehabilitation of Cooling Towers

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client Imam Abdulrahman Bin Faisal University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 9.25 Million Saudi Riyal
Start Date Apr, 2019
Finish Date Apr, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

  • Water Cooled Centrifugal Chillers: 3 nos. Capacity 1,300 TR each (TOTAL 3,900 TR)
  • Mechanical Draft Cooling Towers Open Type: 4 nos. Capacity 3,900 GPM
  • Filtration System: 20 nos. Capacity 54 m³/hr
  • Automatic Sand Trap Filters: 20 nos. Rang between 0.35 mm – 1.2 mm
  • Chilled Water Pumps: 3 nos. TDH 7 bar, Capacity 3,900 GPM
  • Condenser Water Pumps: 3 nos. TDH 3.5 bar, Capacity 3,900 GPM
  • Standby Diesel Generator: 1 no. 1,500 kVA

Mechanical Works for Steam Boilers Network in Medical Center

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jeddah, KSA
End User Ministry of Higher Education
Client King Abdulaziz University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 8.1 Million Saudi Riyal
Start Date Nov, 2018
Finish Date Nov, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

  • Renovation of Boiler Building Replacement of doors and windows,
  • Plastering, painting, ceiling and roof insulation system works.
  • Replacement of (3) nos. Diesel type Steam Boiler
  • Supply, installation, testing & Commissioning of (2) nos. Electric type Steam Boilers and (1) no. Gas type Steam Boiler with steam capacity 1.5 ton/hr.
  • Rehabilitation of (2) nos. Steam Pumps.
  • Supply, installation, Testing & Commissioning of AHU & ducting,
  • RO Unit, Water Softener Unit, Pumps, pipe & fittings and valves,
  • Boiler Plant Fire Fighting System,
  • BMS, Main Distribution Board, cable and cable trays.
  • Underground existing High Pressure Steam Line Test (X-RAY and REPLICA)

Construction of Infrastructure for University City – Central Air Chillers (Phase 1)

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client Imam Abdulrahman Bin Faisal University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 26.08 Million Saudi Riyal
Start Date Nov, 2018
Finish Date May, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

  • Air Cooled Chillers: 8 nos. Capacity 500 TR each (TOTAL 4,000 TR)
  • Chilled Water Pumps: 10 nos. TDH 6.25 bar, Capacity 1,200 GPM
  • Chilled Water Piping System: 350 m, DN800, RTR/GRE, Underground
  • Expansion Tank & Air Separator
  • Split Units and Exhaust Fans
  • FM200 Firefighting System
  • Building Management Control System
  • Fire Alarm System
  • Grounding and Lightning System

KFU Projects for Parking Lots for Female Employees and Students

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Al Ahsa, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant
Type of Project Parking & Landscaping
Total Value (SAR) 5.25 Million Saudi Riyal
Start Date Sep, 2018
Finish Date Jan, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Infrastructure Works

Scope of Work

  • King Faisal University for parking lots for female employees and students.
  • 31000 M2 Area excavation, backfilling, base-coarse and asphalt.
  • All parking area marking, lighting and water drainage system.
  • Parking Gate building all civil, electrical and mechanical work.