Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jubail, KSA
End User Saline Water Conversion Corporation (SWCC)
Client Saline Water Conversion Corporation (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 44 Million Saudi Riyal
Start Date Jul, 2009
Finish Date May, 2010
Total Land Area
Total Built-up Area

Work Description

Carbo steel 60″ pipeline A & B STOPAQ (visco elastic coating) coating Works (13km)

Scope of Work

  • Excavation
  • Removal of existing polyethylene coating
  • Surface preparation (sandblasting of existing pipes)
  • Application of new protective coating (Visco elastic coating)
  • “Holiday” insulations testing
  • Backfilling / compacting / restoration of berm
  • Replacement of fence, post for vent valves etc.
  • Fabrication / installation of reinforced concrete culvert pipes
  • Sand stabilization